Home Up BOE Agenda BOE Minutes BOE Goals BOE Members Recent Projects

 

E-mail addresses for faculty are first initial last name @whufsd.org

Example: jdoe@whufsd.org

 

 

 

 

Recent Building Project History

      In October 1999 district voters approved a $1,932,000 building renovation and reconstruction project to address the following issues:  Electrical wiring upgrade and reconstruction; lighting reconstruction and replacement; media center expansion and reconstruction; parking lot reconstruction and sidewalk replacement; handicap ramp to auditorium lobby; repair and upgrade of high school soccer field and construction of a new bus garage.

In June of 2000 voters again approved a $1,680,000 for the demolition and removal of the old trailers and the construction of six new classrooms in the elementary wing. 

These two projects were combined into one and work began in June 2002.  In April of 2003 students and teachers moved into modern and efficient classrooms and a spacious new K - 12 media center.  


 

An elevator allowing access to the second floor of the high school was  completed in November 2004 at a cost of $300,000 and brought the district into compliance with American Disabilities Act requirements.


 

In March of 2004 voters approved the third phase of construction for $12,700,000.  This project included:  replacement of boilers, piping and temperature controls; replacement of roofing; replacement of the public address and telephone systems; reconstruction of room #206 (including asbestos abatement); auditorium upgrade; high school restroom upgrade; electrical and computer drops throughout the building;  four regular education classroom additions; faculty workroom/office space, restrooms and custodial storage additions, new high school science classrooms; re-key the existing building; construction of a large instructional area; security system access control and cameras and new greeter area at main entrance; locker replacement and renovations in the high school; bus garage; roadway and parking for 50 spaces; baseball and softball field improvements; reconstruction of room #10 into a new main office for K-4; backboards in the elementary gym; renovations to the cafeteria and kitchen ventilation system; computer lab and stairs, ramps and corridor extension.


 

In the fall of 2004, work began on the bus garage and soccer field.  The bus garage is built into the side of the hill near the soccer field, to the left of the auditorium wing.  Construction to the soccer field, located directly opposite Clemente Lane, has been completed and seeded. 

Substantial improvements have been made to the school's baseball and softball fields in the spring and summer of 2005.


 

On May 17, 2005 voters approved replacement of the high school gymnasium bleachers at a cost not to exceed $100,000.  On November 3, 2005 work began to disassemble the existing bleachers.  The new bleachers were installed and were fully operational for the remainder of our 2005-06 basketball season.


 

On January 10, 2006, bids were opened for the third phase of construction.  The district's architectural firm, DCLW, Associates, reviewed all documentation and the district awarded contracts at the January 19, 2006 Board of Education meeting.  Work began on the public address and telephone system.  Construction began in the spring of 2006.  Work on the old science classrooms and other renovations  began after the completion of the new wing, in the summer of 2007.


 

In the summer of 2006 old boilers were removed and a new heating system was installed. A new phone system was installed.  Work also began in the auditorium:  the seats were refurbished; walls were painted; carpeting was installed; stage floor was sanded and refinished; new stage rigging and curtains were installed; new lockers for instruments were delivered; and new lighting and sound equipment were installed.  Other projects included the installation of a new roofing system over the entire building.  There are new student and faculty bathrooms in the high school.  Those rooms were gutted and fitted with all new plumbing, electrical and mechanical fixtures.  Asbestos abatement issues were addressed. 


 

The new wing opened in September 2007 connecting the lower high school hallway with the elementary wing.  Five new state of the art science labs, a multi-purpose room and four additional classrooms serve Middle Schools students for math and English and HS and Middle School students for science classes.  The new multi-purpose room and courtyard is for the use of all K - 12 students.

Offices were re-designed and a new front office was designed for visitors to register and find out information.


L.G. White & Sons has been awarded the contract for the High School 2nd floor ceiling reconstruction project. Construction on this project began on January 21, 2008 and it will continue through March with most of the work taking place on week-ends, February break and after 3:30 when school is in session.


In May 2007 voters approved a project to replace the heating unit ventilators and  the balance of the ceiling replacement project.  The district received State Ed approval and work began June 30, 2008 on the first phase of this project.


 

Project Manager:  Shows Leary Project Management, LLC.

Visit the website at www.showsleary.com for project updates.